Village of Buffalo Grove
$2 million
Design and Construction Engineering
This project rehabilitated 0.50 miles of residential University Drive. Because of frequent breaks, the 10-inch forcemain and eight-inch watermain needed to be replaced and the roadway reconstructed. Challenges included an expedited schedule, an undocumented interconnection with Arlington Heights’s water system and resident coordination. Permitting was required from IEPA, Cook County, and MWRD in an expedited timeframe in order to construct.